Asset management is more than planning and executing maintenance. In accordance with the ISO 55000 standard, it is about systematically managing the entire life cycle of the railway, aimed at an optimal balance between performance, risks, and costs.

GUEST ARTICLE

Jacob Zeeman
Supervisory board member of Dual Inventive and member of the executive board of the DRS Alliance. The Dutch technology company Dual Inventive delivers proven solutions through its proprietary European SIL 4 certified cloud platform and systems, supporting safe and efficient possession management.


Rail networks worldwide face a common pressure: increasing demand on infrastructure coupled with shrinking maintenance windows. Whether in Europe, Asia-Pacific, or the Americas, asset owners are grappling with the same fundamental question: how do you maintain ageing infrastructure to the required standard, with less time and fewer resources? The Netherlands offers one of the most instructive answers.

It is precisely this intersection between measurement, data, analysis, decision, and execution that offers value. The end-to-end principle described is based on a simple premise: the right measures are implemented at the right time, in the right place, with the right technology, and with minimum disruption to rail operations. This is closely in line with the development that ProRail and its contractors in the Netherlands have undergone over the past two decades.

Digitalization of rail maintenance is digitalization of knowledge

  • knowledge about the railway: usage – behaviour – wear and tear – remaining lifespan
  • domain knowledge of maintenance: method – intervention moment – organization

Frontrunner in Europe, privatization of track maintenance

The history of modern Dutch rail maintenance begins in October 1997. Immediately after the privatization of NV Nederlandse Spoorwegen, the maintenance services of NS Railinfraservices and its subsidiary Electrorail were divided among three large contractors in the Netherlands: Strukton, Volker, and BAM. The client was Railinfrabeheer (RIB), predecessor of ProRail.

In the early years, RIB drew up the maintenance concept and the technical risk analysis the contractor had to execute. The main line was inspected every 4 weeks and switches were inspected weekly. Every month, the contractor and RIB carried out a technical inspection to determine which additional work was necessary to maintain the quality of the track. There was no financial incentive to innovate, measure, or predict; the contractor did what was agreed in advance in the annual plan.

Over the years, the Netherlands has become one of the busiest networks in Europe. This had significant consequences for the required track maintenance: more load and deterioration on the network and considerably less time for maintenance. The combination of more intensive use and shrinking night windows forced the sector to think about a fundamentally different approach.

From output based to performance based: a step-by-step contract revolution

Immediately from 1997 onwards, the rail contractors and RIB intensively discussed new contract frameworks for maintenance. RIB wanted to steer remotely, with contractors taking responsibility for safety, technical management, and maintenance execution. That was the beginning of the Output process contracts (OPC). The evolution of contractors gaining more responsibility was a gradual process. In the first years, ProRail remained closely involved in making and validating the maintenance plans. Every year, ProRail managers and contractors undertook inspections to determine core maintenance requirements within the scope of the contract and infrastructure renewal requirements. These renewal works were put out to tender among the certified railway contractors to bid competitively.

The step from OPC to PGO (Performance-based maintenance contracts) was an evolution over several years and required intensive collaboration between ProRail and the contractors. In 2007, the transition from OPC to PGO started. The fundamental aim of the performance-based contracting model is that the operational obligations and results are set and the contractor can use its own expertise and innovative capacity to determine the optimum maintenance approach. ProRail validates the contractor's plans and applies a performance regime (bonus or penalty) to the contractor based on asset performance. For example, the number of asset failures, train disruptions, and fault or defect repair times.

For the contractors, this was a major change and an opportunity to apply their technical knowledge and practical experience into a competitive advantage. They had to make the transition from corrective to preventive maintenance and took the first steps in applying data analysis to plan maintenance. Asset management became the core principle of the maintenance process. Inspections were structured, data was analysed, and contractors invested in new measurement and maintenance techniques. This included the introduction of sensors to collect maintenance data and to predict and prevent defects.

From foot patrol to measurement train: a technical revolution

An important driver behind the development of measurement trains were the increasingly busy networks that require closer and more efficient monitoring. The pressure on obtaining specialist personnel and the rapid development of digital technology have accelerated the development of measurement trains. In the Netherlands, ultrasonic measurement data, geometry, switch inspections, video data (etc.) is used to get a complete picture.

Focus on efficient execution

The capability to digitally inspect and monitor the asset with sensors was not simply about identifying defects or faults within the asset base, but also provides the basis for modelling the rate of deterioration of the asset. The combination of data sources and the development of prediction models supported further efficiency and optimization of maintenance execution in busy rail networks. The requirement to utilize short possessions led to further mechanization and the need for intelligent tamping machines. It also led to the development and use of workplace safety systems that maximized efficiency of shutdowns and enabled remote-controlled safe working during train operation (ZKL3000-RC/ RCS3000)2). This also allowed defects to be resolved safely with minimal impact on train traffic. These last steps completed the digitalization of rail maintenance.

For rail asset owners and maintainers globally, the Dutch experience offers a clear message: digitalization is not simply a technology investment, but rather it is an organizational and contractual transformation. The technology ecosystem only delivers value when it is underpinned by the right incentive structures, the right data governance, and a culture of continuous improvement. As AI and robotics begin to enter the maintenance workflow, those networks that have already built these foundations will be best placed to capture the next wave of productivity gains.